Beginning Phase 2 — as of Sunday, July 22, please access our church from the north, take HWY 370 and turn south on 204th St.  The south entrance will no longer be available and Angus Street will be closed.

Please note that you may need to change your route to get to church during this project:  May 15 – Nov 1

Phase 1 improvements from Glenmore Drive to Angus Street will begin on or about May 15, and be complete by July 6.  During this time, all church traffic will have to use the south parking lot entrance.

Phase 2 improvements will include the intersection of 204th Street and Angus Street, and the widening on Angus Street beginning upon completion of Phase 1.  Work will be completed on or before August 10th.  During this time, all church traffic will have to use the north parking lot entrance, accessing it from Hackberry or 370 and traveling south on 204th St.

Phase 3 improvements will be from Angus Street to Covington Blvd and the work is scheduled to be completed on or before November 1st.

A public Open House has been scheduled on April 19 from 5:00-7:00pm at the City Hall.  A 15-minute presentation of the project overview followed by a question & answer period with representatives from the city, engineering firm and contractors.

Click this link to view a color-coded pdf of the project location with phased implementation areas as well as additional details regarding the Open House.